ESIG with support from Elevate Energy Consulting, and in collaboration with Berkeley Lab and EPRI, is supporting the U.S. Department of Energy (DOE) initiative to facilitate the Forum for the Implementation of Reliability Standards for Transmission (FIRST) as part of the DOE’s Interconnection Innovation e-Xchange (i2X).

Season 1 i2X FIRST Meeting Materials
Download the i2X FIRST Season 1 Recap Summary
This document summarizes season 1 of the i2X FIRST initiative, which provided a foundational exploration of IEEE 2800-2022, its core requirements, and early industry experiences with implementation. Implementation ranges, for example, from original equipment manufacturers (OEMs) readying their inverter products to be compatible with the standard’s technical minimum plant-level requirements; over plant developers and generator owners (GOs) improving the design of new IBR plants to have specified capabilities; to transmission owners (TOs), independent system operators (ISOs), or regional transmission organizations (RTOs) adopting the standard, for example via incorporation into their facility interconnection requirements documents. The forum also addressed ongoing efforts under IEEE P2800.2 to develop robust test and verification procedures to support IBR plant-level capability and performance conformity assessments.
Download the i2X FIRST Season 1 Full Meeting Synopses
Season 1 i2X Monthly Meetings
Reactive Power – Voltage Control Requirements (continued) |April 29, 2025
This meeting focused on reactive power and voltage control requirements, particularly Clause 5 of IEEE 2800-2022, focusing on specific topics such as “Vars at night,” Reactive at sunrise as well as a developer’s perspective on Reactive Power-Voltage Control Requirements.
Interconnection Standards Workshop with the Focus on Post-commissioning Conformity Assessment | March 17, 2025
This half-day hybrid (in-person and online) event focused on Post-commissioning Conformity Assessment with applicable interconnection requirements, specifically learning from the draft IEEE P2800.2. The i2x FIRST workshop covered all stages of IBR plant conformity assessment after the commissioning, including post-commissioning model validation, monitoring and periodic testing.
Session 1: Opening Remarks and IBR Plant Post-commissioning Model Validation
Session 2: IBR Plant Post-commissioning Monitoring and Periodic Testing
Power Quality and Protection Requirements | February 25, 2025
This meeting focused on power quality and protection requirements, particularly Clauses 8 and 9 of IEEE 2800-2022.
Reactive Power – Voltage Control Requirements | December 17, 2025
This meeting discussed reactive power voltage control requirements, specifically focusing on standards outlined in clause five of 2800-2022 from the Institute of Electrical and Electronics Engineers.
Active-Power—Frequency Response Requirements | November 26, 2024
This meeting discussed active power frequency response requirements, specifically focusing on standards outlined in clause six of 2800-2022 from the Institute of Electrical and Electronics Engineers.
Conformity Assessment | October 24, 2024
This event focused on conformity assessment with applicable interconnection requirements, specifically learning from the draft IEEE P2800.2
View session recordings:
- Session 1: Opening Remarks and Background Information
- Session 2: IBR Plant Modeling and IEEE P2800.2 Design Evaluation
- Session 3: Model Validation
- Session 4: “As-Built” Evaluation and Commissioning Testing
Measurement Data for Performance Monitoring and Model Validation | September 24, 2024
This meeting focused on interconnection measurement data, with discussions and presentations on IEEE 2800-2022 Clause 11 and NERC Protection and Control (PRC)-028, the need for disturbance monitoring, and an update from the NERC technical conference.
Ride-Through Requirements and Original Equipment Manufacturer (OEM) Readiness – Continued | August 20, 2024
This meeting continued the focus on manufacturer readiness to conform with new inverter-based resource (IBR) ride through requirements, specifically those outlined in IEEE 2800-2022 Clause 7. It included presentations from ESIG, GE Vernova, Sungrow, and NERC, as well as a Q&A and interactive group discussion.
Ride-Through Requirements and Original Equipment Manufacturer (OEM) Readiness | July 30, 2024
This meeting focused on manufacturer readiness to conform with new inverter-based resource (IBR) ride through requirements, specifically those outlined in IEEE 2800-2022 Clause 7. It included a Q&A and group discussion on backward-compatibility and conformity of IBR plants with new ride through requirements and presentations on OEM perspectives.
IEEE2800 Ride Through Requirements | June 25, 2024
This meeting centered on IEEE2800 Ride Through Requirements (e.g., voltage, frequency, phase jump, consecutive ride through) including the purpose of requirements, meaning, implementation, conformity assessment during interconnection process and commissioning (elements of IEEE2800.2), post commissioning assessment (elements of IEEE2800.2), challenges faced and lessons learned from early adopters, original equipment manufacturer (OEM) readiness, and NERC Protection and Control (PRC)-024/029 alignment.
Introduction of Evolving Standards Landscape | May 28, 2024
This meeting discussed interconnection-related standards and how they are evolving. Topics discussed were NERC disturbance events, IEEE2800 and its adoption, IEEE2800.2 development, FERC Order 901 and the required NERC Work Plan, and ongoing NERC standard development efforts. The presenters were Julia Matevosyan (ESIG), Will Gorman (Lawrence Berkeley National Laboratory), and Jens Boemer (EPRI).